Construct the following project plan in MS Project.
ID | Name | Duration | Effort | Predecessors | Milestone |
---|---|---|---|---|---|
1 | Build House | xx days | xx days | No | |
2 | Develop Plan | xx days | xx days | No | |
3 | Hire architect | 7 days | 21 hrs | No | |
4 | Present architect with specifications | 1 day | 3 hrs | 3 | No |
5 | Rework the blueprints | 7 days | 14 hrs | 4 | No |
6 | Hire subcontractor | 4 days | 8 hrs | 3 | No |
7 | Finalize plans with architect and subcontractor | 0 days | 0 days | 5,6 | Yes |
8 | Construct House | xx days | xx days | 2 | No |
9 | Buy lot | 2 days | 7 hrs | No | |
10 | Pour foundation | 2 days | 16 hrs | 9 | No |
11 | Construct frame | 2 wks | 70 hrs | 10 | No |
12 | Finished rough exterior carpentry | 0 days | 0 days | 11 | Yes |
13 | Rough Interior Work | xx days | xx days | 12 | No |
14 | Rough in electrical | 1 wk | 25 hrs | No | |
15 | Rough in plumbing | 1 wk | 30 hrs | No | |
16 | Install doors and windows | 2 days | 16 hrs | No | |
17 | Sheetrock | 3 days | 21 hrs | 14,15,16 | No |
18 | Finished rough interior work | 0 days | 0 days | 17 | Yes |
19 | Finish Work | xx days | xx days | 18 | No |
20 | Finish carpentry | 1.5 wks | 82 hrs | No | |
21 | Finish electrical | 2 days | 15.5 hrs | No | |
22 | Finish plumbing | 2 days | 14 hrs | No | |
23 | House Completed | 0 days | 0 days | 19 | Yes |
After constructing the project, complete the following steps